B 248: Road renewal between Salzgitter-Bad and Salzgitter-Lobmachtersen

From Monday, 15.04.2024, the construction work between Salzgitter-Bad and
Salzgitter-Lobmachtersen will be resumed. This was announced by the Lower Saxony State Authority for Road Construction and Transport.

Work will be carried out simultaneously in two construction phases with half and full road closures. The closures are expected to be lifted by the beginning of June.

  1. Construction phase: Between Lobmachtersen and Beinum, the remaining work, such as verge work, placing delineators, installing crash barriers and setting up signage, will be carried out under a half-side closure. Traffic will be diverted past the construction site.
  2. Construction phase: For the work between Salzgitter-Bad and Beinum, it is necessary to close the road to traffic completely.
    The detour for this will be via the state road 472 from Salzgitter-Bad, Gebhardshagen to district road 30 Watenstedt and then back onto the federal road 248. The detour for the opposite direction will be in the opposite direction.

Background: Road resurfacing work began in June 2023 on a stretch of around 5.1 kilometers of the B248 between Salzgitter-Bad and Salzgitter-Lobmachtersen. The work had to be discontinued at the end of last year due to the extreme weather conditions.